COORDINACION GENERAL DE ADMINISTRACIONES PORTUARIAS INTEGRALES
Administración Portuaria Integral de Altamira, S.A. de C.V.
AVANCE FISICO-FINANCIERO DEL PROGRAMA DE OBRA PUBLICA 2004.
REGISTRO DE SEGUIMIENTO A LAS PARTIDAS DE INVERSIÓN.         API-ALT-GOI-F-42
     PERIODO:  AL TERCER TRIMESTRE 2004
No. O  B  R  A CANTIDAD/  MONTO   P  R  O  G  R  A  M  A
      U. DE MEDIDA AUTORIZADO   ENE  FEB MAR ABR MAY JUN JUL AGO SEP OCT NOV DIC
1 Dragado de construcción metros cúbicos $83,151.38 P 0.00% 0.00% 0.00% 6.34% 11.43% 13.71% 28.44% 45.64% 70.05%      
          R 0.00% 0.00% 0.01% 0.01% 0.15% 0.15% 18.04% 22.05% 62.61%      
  INICIO 15/04/2004   P 0.00 0.00 0.00 5,271.90 9,508.00 11,408.00 23,651.38 37,951.38 58,251.38      
  TERMINO 15/11/2004     R 0.00 0.00 7.08 7.08 127.23 8,432.74 8,522.74 18,342.62 52,067.93      
2 Construcción líneas de agua obra $1,000.00 P 0.00% 0.00% 0.00% 30.00% 37.50% 45.00% 100.00% 100.00% 100.00%      
          R 0.00% 0.00% 0.00% 0.00% 32.09% 59.00% 66.85% 66.85% 88.63%      
  INICIO 01/04/2004     P 0.00 0.00 0.00 300.00 375.00 450.00 1,000.00 1,000.00 1,000.00      
  TERMINO 30/12/2004     R 0.00 0.00 0.00 0.00 320.96 320.96 406.40 584.16 886.32      
3 construcción de vialidades obra $8,000.00 P 0.00% 0.00% 0.00% 0.00% 0.00% 30.00% 47.50% 65.00% 82.50%      
          R 0.00% 8.17% 13.74% 13.82% 12.34% 18.74% 23.75% 25.24% 33.68%      
  INICIO 15/06/2004     P 0.00 0.00 0.00 0.00 0.00 2,400.00 3,800.00 5,200.00 6,600.00      
  TERMINO 30/12/2004     R 0.00 653.76 1,099.30 1,106.38 987.95 1,341.11 1,900.11 2,019.97 2,695.08      
4 Construcción líneas eléctricas obra $4,650.00 P 0.00% 0.00% 0.00% 0.00% 0.00% 30.00% 53.33% 76.66% 100.00%      
          R 0.00% 0.54% 0.54% 0.54% 0.54% 5.54% 5.54% 5.54% 7.58%      
  INICIO 15/06/2004     P 0.00 0.00 0.00 0.00 0.00 1,395.00 2,480.00 3,565.00 4,650.00      
  TERMINO 31/12/2004     R 0.00 25.13 25.13 25.13 25.13 25.13 25.13 25.13 34.40      
5 Alumbrado Público obra $3,000.00 P 0.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00%      
          R 0.00% 49.36% 91.90% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00%      
  INICIO 02/01/2004     P 900.00 3,000.00 3,000.00 3,000.00 3,000.00 3,000.00 3,000.00 3,000.00 3,000.00      
  TERMINO 30/12/2004     R 0.00 1,480.88 2,757.12 4,234.62 5,593.52 5,593.52 5,593.52 5,593.52 6,078.40      
6 Construcción vías férreas obra $1,000.00 P 0.00% 30.00% 65.00% 82.50% 100.00% 100.00% 100.00% 100.00% 100.00%      
          R 0.00% 186.07% 355.05% 95.00% 95.00% 95.00% 100.00% 100.00% 100.00%      
  INICIO 15/02/2004     P 0.00 300.00 650.00 825.00 1,000.00 1,000.00 1,000.00 1,000.00 1,000.00      
  TERMINO 30/12/2004     R 0.00 1,860.77 3,550.53 4,109.31 4,277.83 4,277.83 4,523.68 4,620.46 4,620.46      
7 Construcción gasoducto 12" Ø obra $7,500.00 P 0.00% 15.00% 50.93% 51.66% 53.81% 65.02% 100.00% 100.00% 100.00%      
          R 0.00% 0.00% 26.06% 28.21% 75.92% 89.43% 91.00% 98.00% 99.00%      
  INICIO 15/02/2004     P 0.00 1,125.00 3,820.08 3,875.00 4,036.00 4,877.00 7,500.00 7,500.00 7,500.00      
  TERMINO 15/07/2004     R 0.00 0.00 1,954.60 2,116.04 5,694.67 7,847.22 7,858.24 8,576.61 8,887.27      
8 Construcción gasoducto 48" Ø obra $13,000.00 P 0.00% 0.00% 28.41% 29.20% 30.00% 31.58% 42.30% 53.84% 53.84%      
          R 0.00% 0.00% 0.00% 0.00% 0.01% 0.01% 0.01% 0.01% 0.01%      
  INICIO 15/03/2004     P 0.00 0.00 3,693.80 3,796.90 3,900.00 4,106.00 5,499.80 8,500.00 8,500.00      
  TERMINO 15/12/2004     R 0.00 0.00 0.00 2.36 2.36 2.36 2.36 2.36 2.36      
9 Drenaje pluvial obra $4,000.00 P 0.00% 0.00% 0.00% 1.48% 30.00% 36.50% 58.00% 72.00% 86.00%      
          R 0.00% 0.00% 0.00% 0.00% 1.48% 10.00% 14.21% 16.61% 35.00%      
  INICIO 15/05/2004     P 0.00 0.00 0.00 0.00 1,200.00 1,460.00 2,320.00 2,880.00 3,440.00      
  TERMINO 15/10/2004     R 0.00 0.00 0.00 59.55 59.55 59.55 568.42 664.70 1,400.13      
10 Delimitación de derechos de vía y  obra $1,000.00 P 0.00% 0.00% 0.00% 0.00% 30.00% 47.50% 100.00% 100.00% 100.00%      
  otras áreas restringidas.     R 0.00% 0.00% 0.00% 0.00% 0.00% 10.00% 0.02% 42.04% 45.00%      
  INICIO 15/05/2004     P 0.00 0.00 0.00 0.00 300.00 475.00 1,000.00 1,000.00 1,000.00      
  TERMINO 15/07/2004     R 0.00 0.00 0.00 0.00 0.00 0.00 22.00 420.42 1,185.30      
11 Planta de tratamiento de agua obra $1,000.00 P 0.00% 30.00% 75.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00%      
          R 0.00% 0.00% 0.00% 0.00% 0.00% 6.00% 6.00% 6.00% 6.00%      
  INICIO 15/02/2004     P 0.00 300.00 750.00 1,000.00 1,000.00 1,000.00 1,000.00 1,000.00 1,000.00      
  TERMINO 16/04/2004     R 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00      
12 Construcción de centro táctico de  obra $250.00 P 0.00% 0.00% 30.00% 65.00% 100.00% 100.00% 100.00% 100.00% 100.00%      
  control aduanero.     R 0.00% 0.00% 0.00% 0.00% 0.00% 5.00% 5.00% 5.00% 10.40%      
  INICIO 15/03/2004     P 0.00 0.00 75.00 162.50 250.00 250.00 250.00 250.00 250.00      
  TERMINO 31/12/2004     R 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 26.00      
13 Obra civil y eléctrica para colocación obra $1,500.00 P 0.00% 0.00% 0.00% 52.16% 78.33% 85.00% 100.00% 100.00% 100.00%      
  de detector de rayos gamma     R 0.00% 0.00% 0.00% 25.09% 27.28% 100.00% 100.00% 100.00% 100.00%      
  INICIO 15/04/2004   P 0.00 0.00 0.00 782.50 1,175.00 1,275.00 1,500.00 1,500.00 1,500.00      
  TERMINO 31/12/2004     R 0.00 0.00</